Online Formal Notice Forms
These forms are listed in the order they should be submitted.
'Start of Works' Notice
(First form, prior to starting any works)
At least two full working days before the day on which building work starts, the person carrying out the work must give a notice to us setting out their intention to start the work and the date that work is to start.
CLICK HERE for Formal Notice of 'Start of Works' form
Commencement Notice
(Second form, after legal commencement (15% of works or other statutorily defined stage))
Not more than five working days after the day on which the work is to be regarded as commenced the person carrying out the work must give a notice to that effect to us.
CLICK HERE for Formal Notice of Commencement form
Online Formal Completion of Works Declaration Forms
(Completion declarations, prior to completion inspection)
Prior to booking a completion inspection, the Client, Principal Designer and Principal Contractor are required to make formal legal declarations relating to their respective roles as Dutyholders
CLICK HERE for Formal Completion Declaration by Client form
CLICK HERE for Formal Completion Declaration by Principal Designer form
CLICK HERE for Formal Completion Declaration by Contractor form